122
Chapter 10: Project Management (Project Mode)
Reloading the backup Project
Follow the steps below to reload the backup Project from the external SCSI device or DAT recorder onto the
current disk.
Loading from the SCSI device
1. On the Project screen, press the [F1] (
MORE
) key, then the [F5] (
RELOAD
) key.
The following screen appears.
2. Set the
Device
fields to SCSI.
The following screen appears.
1
2
1
Source disk
This field is used to select a disk that has the stored backup data.
2
Current disk ID
This field indicates the current disk that the backup data to be loaded.
3. In the
Source disk
field (
1
), select the SCSI ID of the disk from which you wish to reload the
backup data.
4. Press the [F5] (
DO IT
) key.
The following screen appears.
1
2
1
Current disk free
Indicates the free space on the current disk.
2
Project list
Displays the list of Projects stored on the backup disk.
5. Use the cursor to select the desired Project to reload.
➸
NOTE :
You cannot reload a Project of a size larger than the free space displayed in the
Current disk
free
field (
1
).
6. Press the [F5] (
DO IT
) key to reload the backup data.
The reload operation starts. When it is completed the display returns to the Project screen.