37
Scholar V Installation & Startup Manual 07/2016 New
HOLES TO SECURE BASE STAND TO FLOOR
HOLES TO HOLD SCHOLAR III TO BASE PAN
Figure 1. Top View of Base Stand
Also, recheck the locations of the electrical and condensate stub-outs to ensure they
are located properly, relative to the cabinet knock-out openings as shown in the
Installation and Start-Up Manual, Figures 3 and 4.
IMPORTANT
STUBOUTS SHOULD BE LOCATED (FROM THE FLOOR OR WALL) TO ALIGN WITH
SELECTED CABINET KNOCK OUT ON THE CABINET, AS SHOWN IN FIGURE 3. THIS
IS A REQUIREMENT IF A BASE STAND IS TO BE INSTALLED AND STUBOUTS ARE
COMING THROUGH THE FLOOR
Lastly, re-measure to be sure that the wall opening for the Scholar V heat pump and air
conditioner air box is located properly, taking the height of the base stand into account,
before proceeding to install the base stand.