2.5 Description of basic functionality
2.5.1
Switching sequence / Automatic
2.5.1.1 Source 1 Priority
(Source 2 = Generator)
Switching sequence summary:
• An anomaly occurs on the source 1
• Override momentary S1 outage delay
• Generator start
• Source 2 OK
• Transfer from S1 to S2 delay
• Pre-transfer signal on
• Load shed signal on
• Pre-transfer S1 to S2 delay
• Load shed delay
• Transfer switch to the position O (only
with delayed transition I-O-II type and
at least one phase exists in source 1)
• Center-Off delay (only with delayed
transition I-O-II type, delay is zero when
all phases are missing in source 1)
• Transfer switch to the position II
(source 2)
• Post-transfer S1 to S2 delay
• Pre-transfer signal off
Retransfer sequence summary:
• The source 1 is restored
• Transfer from S2 to S1 delay
• Pre-transfer signal on
• Pre-transfer S2 to S1 delay
• Transfer switch to the position O (only
with delayed transition I-O-II type)
• Center-off delay (only with Delayed tran-
sition I - O - II type)
• Transfer switch to the position I
(source 1)
• Load shed signal off
• Generator stop delay
• Post-transfer S2 to S1 delay
• Pre-transfer signal off
• Generator stop
• Source 2 off
Summary of Contents for TruONE ATS
Page 2: ......
Page 6: ...6 TruONE ATS INSTALL ATION AND OPER ATING INSTRUCTION 1 ...
Page 151: ... Notes ...
Page 152: ... Notes ...
Page 153: ... Notes ...
Page 154: ... Notes ...
Page 155: ... Notes ...
Page 156: ... Notes ...
Page 157: ... Notes ...
Page 159: ......