Maintenance
Operating Mechanism Maintenance
12
1HSB515409-100 en rev2
4.2 Preparations for maintenance
The following should be done before maintenance is started:
1.
Switch the circuit-breaker to the open position.
2.
Isolate and earth.
3.
Switch off the motor current.
4.
Perform a Close-Open operation so that the spring battery in the operating
mechanism is discharged.
5.
Switch off the control voltage and, if necessary, also the heater voltage.
Figure 4-5. Control panel
Item
1
Control panel
2
Control switch On/Off
3
Switch Local/Remote
4
Electric counter
5
Spring indicator
1
3
5
2
4
B20009