Operating and Maintenance Instructions
Inspection intervals
1HSB435409-100 en1
17
9.
Tightness of the SF
6
gas
•
Density monitoring
15 years or 5,000 mech. CLOSE/
OPEN operations.
Check the density switches and
signal/blocking circuits.
Accurancy test of the pressure gauge
must be done at standard reference
atmosphere i.e. +20
˚C
and 101.3 kPa
(1013 mbar).
Remove the density switch from the
circuit-breaker for checking of function.
N.B. Min permissible voltage for test
of the circuits in the density
switch (30 V).
See applicable Assembly Instruction for
the circuit-breaker.
10.
Blocking relays
15 years or 5,000 mech. CLOSE/
OPEN operations.
The relays shall close when a density
switch is pulled out from a pole
pressurized to filling pressure.
11.
Corrosion
15 years or 5,000 mech. CLOSE/
OPEN operations.
Outside:
Visual check, particularly check
protected components in non heated
compartments, pull-rod system, clevis
couplings, springs.
Treat with anti-rust oil if necessary.
See
Chapter 2.2.4
and Manual
1HSB515409-100 for BLG 1002A or
1HSB535409-100 for BLK 222.
12a.
Lubrication
15 years or 5,000 mechanical
Close-Open operations.
Inspect and lubricate the latches.
See
Chapter 2.1.5
,
Chapter 2.2.3
and
Manual 1HSB515409-100 for BLG
1002A or 1HSB535409-100 for BLK
222.
To be inspected
Inspection interval
Measures / Instructions /
Tools
Summary of Contents for SF6 LTB 245E1 BLG 1002A
Page 1: ...Product Manual 1HSB435416 2 en Rev 1 LTB 245E1 BLG 1002A 3 pole operation ...
Page 92: ...ABB Switchgear SF6 Circuit Breaker Circuit breakers HPL and LTB 1HSB445409 1 en0 Lubricants ...
Page 198: ......
Page 199: ......
Page 209: ......
Page 210: ......