Note
Action
xx2000000449
Jog the robot into position:
•
Axis-1: 0°
•
Axis-2: -70°
•
Axis-3: +70° (approximately)
•
Axis-4: 0°
•
Axis-5: -45°
•
Axis-6: +90° (if DressPack is installed)
2
DANGER
Turn off all:
•
electric power supply
•
hydraulic pressure supply
•
air pressure supply
to the robot, before entering the safeguarded
space.
3
See
Draining the axis-2 gearbox on
Begin draining the gearbox.
4
Attaching lifting accessories to the lower and upper arm
Note
Action
CAUTION
The weight of the complete upper and lower arm
together is
IRB 5720-180/2.6, IRB 5720-155/2.6 LID: 440 kg
IRB 5720-125/3.0, IRB 5720-90/3.0 LID: 390 kg
All lifting accessories used must be sized accord-
ingly.
1
Lifting eye: 3HAC16131-1
xx2100001413
Fit a lifting eye to the wrist.
2
Continues on next page
476
Product manual - IRB 5720
3HAC079195-001 Revision: A
© Copyright 2022 ABB. All rights reserved.
5 Repair
5.9.2 Replacing the axis-2 gearbox
Continued
Summary of Contents for IRB 5710
Page 1: ...ROBOTICS Product manual IRB 5720 ...
Page 8: ...This page is intentionally left blank ...
Page 14: ...This page is intentionally left blank ...
Page 36: ...This page is intentionally left blank ...
Page 186: ...This page is intentionally left blank ...
Page 580: ...This page is intentionally left blank ...
Page 604: ...This page is intentionally left blank ...
Page 609: ......