Identification: MD-AL-GI-00
Rev. 1.0 of 21/07/2021 - Application: GID
User’s Manual 1PH 3000TLM-6000TLM-V3
Rev. 1.0 21/07/2021
Note
Both MPPT inputs of the inverter should be populated, even if the system only has one string. If the strings
are arranged in parallel, it is recommended to use a Y or T connection cable to double the input currents
from the PV array and to populate all the MPPT inputs of the inverter, as shown in the figure. If the string
arrangement is independent, simply connect the two strings to the two MPPTs of the inverter.
Figure 11 – Y-branch connection cable for solar panels
Check the polarity of the PV string to ensure the correct connection of the cables
to the string.
Do not connect the positive or negative polarities of the PV string to the ground.
Note