Chapter 3: Configuration and commissioning
68
ZP1-F Series Installation Manual
Commissioning
Before commissioning the control panel
Before commissioning the control panel, make sure that:
• The control panel has been correctly installed
• The mains power is 110 VAC or 230 VAC, is connected correctly, and
complies with all requirements described in “Connecting the mains power
supply” on page 18
• There are no short or open circuits in any of the zone circuits
• All zones have the correct end-of-line termination, as described in
“Terminating zones” on page 11
• All manual call points have the correct resistance for alarm identification, as
described in “Connecting manual call points” on page 12
• Polarity is observed for all sounder circuits and that all end-of-line resistors
are installed, as described in “Connecting sounders or other notification
devices to supervised outputs” on page 16
• Any optional equipment installed (fire routing, alarm, and fault relays, etc.) is
correctly connected
• The batteries are connected correctly, and comply with all requirements
described in “Connecting the batteries” on page 20
• All fire alarm system configuration complies with the corresponding operating
mode and local regulations.
Содержание ZP1-F2
Страница 1: ...ZP1 F Series Installation Manual P N 501 415603 1 60 ISS 12DEC22...
Страница 78: ...Chapter 3 Configuration and commissioning 72 ZP1 F Series Installation Manual...
Страница 82: ...Chapter 4 Maintenance 76 ZP1 F Series Installation Manual...
Страница 92: ...Chapter 5 Technical specifications 86 ZP1 F Series Installation Manual Figure 23 Eight zone cabinet with cover...
Страница 94: ...Chapter 5 Technical specifications 88 ZP1 F Series Installation Manual...
Страница 106: ...Appendix A Configuration presets 100 ZP1 F Series Installation Manual...
Страница 110: ...Appendix B Regulatory information 104 ZP1 F Series Installation Manual...
Страница 113: ......