UNIT START-UP CHECKLIST
MODEL NO.: _________________________________
SERIAL NO.: ______________________________________
SOFTWARE VERSION _________________________
TECHNICIAN: ____________________________________
DATE: _______________________________________
PRE-START-UP:
VERIFY THAT ALL PACKING MATERIALS HAVE BEEN REMOVED FROM UNIT
REMOVE ALL COMPRESSOR SHIPPING HOLDDOWN BOLTS AND BRACKETS PER INSTRUCTIONS
VERIFY INSTALLATION OF ECONOMIZER HOOD PER INSTRUCTIONS
(including relocation of OAT sensor if necessary)
VERIFY INSTALLATION OF ALL OPTIONS AND ACCESSORIES
VERIFY PROPER INSTALLATION AND LOCATION OF STATIC PRESSURE TRANSDUCERS
(Supply Duct and Building Pressure when applicable)
VERIFY THAT ALL ELECTRICAL CONNECTIONS AND TERMINALS ARE TIGHT
VERIFY INSTALLATION AND LOCATION OF LAT SENSORS (multi-staged gas, SCR electric, hydronic heat only)
CHECK GAS PIPING FOR LEAKS (48A ONLY)
CHECK THAT RETURN-AIR FILTER AND OUTDOOR-AIR FILTERS ARE CLEAN AND IN PLACE
VERIFY THAT UNIT IS LEVEL WITHIN TOLERANCES FOR PROPER CONDENSATE DRAINAGE
CHECK FAN WHEELS AND PROPELLERS FOR LOCATION IN HOUSING/ORIFICE, AND SETSCREW IS TIGHT
VERIFY THAT FAN SHEAVES ARE ALIGNED AND BELTS ARE PROPERLY TENSIONED
VERIFY THAT SUCTION, DISCHARGE, AND LIQUID SERVICE VALVES ON EACH CIRCUIT ARE OPEN
VERIFY THAT CRANKCASE HEATERS HAVE BEEN ON 24 HOURS BEFORE START-UP
START-UP:
ELECTRICAL
SUPPLY VOLTAGE
L1-L2
__________
L2-L3 __________
L3-L1
__________
COMPRESSOR AMPS — COMPRESSOR NO. 1 L1
__________
L2
__________
L3 _________
COMPRESSOR AMPS — COMPRESSOR NO. 2 L1
__________
L2
__________
L3 _________
SUPPLY FANS AMPS
(CV/SAV)
_________
EXHAUST FAN AMPS __________
(VAV)
_________ *
*VAV fan supply amps reading must be taken with a true RMS meter for accurate readings.
TEMPERATURES
OUTDOOR-AIR TEMPERATURE
__________ F DB (Dry Bulb)
RETURN-AIR TEMPERATURE
__________ F DB __________ F WB (Wet Bulb)
COOLING SUPPLY AIR
__________ F
GAS HEAT SUPPLY AIR
__________ F (48A ONLY)
ELECTRIC HEAT SUPPLY AIR
__________ F (50A ONLY, IF EQUIPPED)
NOTE: To avoid injury to personnel and damage to equipment or
property when completing the procedures listed in this start-up
checklist, use good judgment, follow safe practices, and adhere to
the safety considerations/information as outlined in preceding sec-
tions of this Controls, Start-Up, Operation, Service and Trouble-
shooting document.
Содержание Carrier Weathermaker 48A2
Страница 105: ...105 Fig 20 Typical Main Control Box Wiring Schematic 48 50A2 A3 A4 A5 Units...
Страница 106: ...106 Fig 21 Typical Auxiliary Control Box Wiring Schematic...
Страница 107: ...107 Fig 22 Typical 2 Stage Gas Heat Wiring Schematic Size 060 Units Shown a48 8357...
Страница 108: ...108 TO NEXT PAGE Fig 23 Typical Staged Gas Heat Wiring Schematic Size 060 Units Shown A48 7296...
Страница 109: ...109 Fig 23 Typical Staged Gas Heat Wiring Schematic Size 060 Units Shown cont A48 8358...
Страница 110: ...110 Fig 24 Typical Electric Heat Control Schematic 50 Series Size 060 Units Shown a50 8228...
Страница 111: ...111 Fig 25 Typical Power Schematic 48 50A2 A3 A4 A5 060 Unit Shown...
Страница 112: ...112 Fig 26 Typical Low Ambient Controls Option Wiring...
Страница 113: ...113 Fig 27 Typical Small Chassis Component Location Size 020 035 Units...
Страница 114: ...114 Fig 28 Typical Large Chassis Component Locations Size 040 060 Units...
Страница 118: ...118 Fig 30 Economizer Control Board ECB1 and VAV Control Board ECB2 A48 7706...
Страница 142: ...142 A48 3733 Fig 56 Main Burner Removal...
Страница 176: ...176 APPENDIX C VFD INFORMATION cont Fig F Internal Enclosure Fan Replacement A48 7716...