8
Figure 2A: Chimney Vented Boiler - Minimum Installation Clearances To Combustible Materials (Inches)
A.
INSPECT SHIPMENT
carefully for any signs of
damage.
1. All equipment is carefully manufactured, inspected and
packed. Our responsibility ceases upon delivery of crated
boiler to the carrier in good condition.
2. Any claims for damage or shortage in shipment must be
filed immediately against the carrier by the consignee.
No claims for variances from, or shortage in orders, will
be allowed by the manufacturer unless presented within
sixty (60) days after receipt of goods.
B.
LOCATE BOILER
in front of final position before removing
crate. See Figure 1.
1. LOCATE so that vent pipe connection to chimney will
be short and direct.
2. BOILER IS SUITABLE FOR INSTALLATION ON
COMBUSTIBLE FLOOR. Boiler cannot be installed
on carpeting.
3. FOR BASEMENT INSTALLATION, provide a solid
elevated base, such as concrete, if floor is not level, or if
water may be encountered on floor around boiler.
4. PROVIDE RECOMMENDED SERVICE CLEARANCE,
if applicable, as follows:
a. Clearance from Jacket Front Panel -
•
24" for servicing burner
•
24" for flueway cleaning (MPO-IQ84 thru 147)
•
30" for flueway cleaning (MPO-IQ189)
•
36" for flueway cleaning (MPO-IQ231)
b. Clearance from Jacket Side Panels -
•
19" for burner swing door, if opened fully with
burner mounted, otherwise 1" with b u r n e r
removed.
•
12" access clearance to service rear of
boiler if other side clearance is less
than 12".
• 3
" minimum if other side clearance is 12" or
larger to access and service rear of boiler.
c. Clearance from Jacket Rear Panel -
•
12" minimum for rear smokebox cleaning
(Note: This dimension will also be controlled
by horizontal to vertical to horizontal smokepipe
arrangement -
Chimney Vent
(see Figures 2A
and 15).
•
24" for rear smokebox cleaning and disconnecting
vent pipe from appliance adapter for servicing (if
required) -
Direct Vent
(see Figure 2B).
5. For minimum clearances to combustible materials. See
Figures 2A and 2B.
NOTICE
Clearance to venting is for single wall vent pipe. If
Type L vent is used, clearance may be reduced to the
minimum required by the vent pipe manufacturer.
I. PRE-INSTALLATION
NOTES:
1. Listed clearances comply with American National Standard ANSI/
NFPA 31, Installation of Oil Burning Equipment.
2. MPO-IQ boilers can be installed in rooms with clearances from
combustible material as listed above. Listed clearances cannot be
reduced for alcove or closet installations.
3. For reduced clearances to combustible material, protection must be
provided as described in the above ANSI/NFPA 31 standard.
Содержание MPO - IQ
Страница 6: ...6 Figure 1 MPO IQ84 Thru MPO IQ231 Water Boiler ...
Страница 22: ...22 Figure 11 Boiler Removal from Skid III UNIT PAK BOILER ASSEMBLY TRIM CONTROLS continued ...
Страница 27: ...27 Figure 13A Recommended Water Piping for Circulator Zoned Heating Systems IV WATER Boiler PIPING continued ...
Страница 28: ...28 Figure 13B Recommended Water Piping for Zone Valve Zoned Heating Systems IV WATER Boiler PIPING continued ...
Страница 42: ...42 Figure 28A Schematic Wiring Diagram VII ELECTRICAL continued ...
Страница 43: ...43 Figure 28B Schematic Wiring Diagram Burner Options VII ELECTRICAL continued ...
Страница 44: ...44 Figure 28C Ladder Diagram VII ELECTRICAL continued ...
Страница 70: ...70 Bare Boiler Assembly XIV Repair Parts continued ...
Страница 72: ...72 Jacket Assembly XIV Repair Parts continued ...
Страница 74: ...74 MPO IQ84 Thru MPO IQ231 Water Boilers Trim and Controls XIV Repair Parts continued ...
Страница 78: ...78 Beckett AFG Burner XIV Repair Parts continued ...
Страница 80: ...80 Beckett NX Burner XIV Repair Parts continued ...
Страница 92: ...92 U S Boiler Company Inc P O Box 3020 Lancaster PA 17604 1 888 432 8887 www usboiler net ...