18
Figure 8: Baffle Orientation in Flueways
Step a.
Install stainless steel baffles provided in
miscellaneous parts carton as follows, refer to Table
3 and Figure 8:
•
Model MPO-IQ84 - To install flueway baffle in 3
rd
pass on left side of boiler, hold baffle with word
"Left" readable at the top. Slide baffle in flueway
until position tab touches fins on left side of 3
rd
pass flueway. To install flueway baffle in 3
rd
pass
flueway on right side of boiler, hold baffle with
word "Right" readable at the top. Slide baffle in
flueway until position tab touches fins on right
side of 3
rd
pass flueway.
•
Model MPO-IQ115 - To install flueway baffle in
3
rd
pass on left side of boiler, hold baffle with word
“Left” readable at the top. Slide baffle in flueway
until position tab touches fins on left side of 3
rd
pass flueway. To install flueway baffle in 3
rd
pass
flueway on right side of boiler, hold baffle with
word “Right” readable at the top. Slide baffle in
flueway until position tab touches fins on right
side of 3
rd
pass flueway. To install flueway baffle
in 2
nd
pass on left side of boiler, hold baffle with
word “Left” readable at the top. Slide baffle in
flueway until position tab touches fins on left side
of 3
rd
pass flueway. To install flueway baffle in 2
nd
pass flueway on right side of boiler, hold baffle
with word “Right” readable at the top. Slide
baffle in flueway until position tab touches fins
on right side of 3
rd
pass flueway.
•
Models MPO-IQ147, MPO-IQ189 and MPO-
IQ231 - To install flueway baffle in 2
nd
pass
flueway on left side of boiler, hold baffle with
word "Left" readable at the top. Slide baffle in
flueway until position tab touches fins on right
side of 2
nd
pass flueway. To install flueway baffle
in 2
nd
pass flueway on right side of boiler, hold
baffle with word "Right" readable at the top. Slide
baffle in flueway until position tab touches fins
on left side of 2
nd
pass flueway.
NOTE:
2
nd
and 3
rd
pass flueway baffle are not
interchangeable.
6.
Close the burner swing door
and securely seal the door
to the boiler front section by reinstalling the hardware and
securing the door using procedure previously outlined in
Paragraph D of this section.
NOTICE
When securing burner swing door make sure door
is drawn-in equally on both sides.
II. PACKAGED BOILER ASSEMBLY - TRIM & CONTROLS (cont'd)
Содержание MPO - IQ
Страница 6: ...6 Figure 1 MPO IQ84 Thru MPO IQ231 Water Boiler ...
Страница 22: ...22 Figure 11 Boiler Removal from Skid III UNIT PAK BOILER ASSEMBLY TRIM CONTROLS continued ...
Страница 27: ...27 Figure 13A Recommended Water Piping for Circulator Zoned Heating Systems IV WATER Boiler PIPING continued ...
Страница 28: ...28 Figure 13B Recommended Water Piping for Zone Valve Zoned Heating Systems IV WATER Boiler PIPING continued ...
Страница 42: ...42 Figure 28A Schematic Wiring Diagram VII ELECTRICAL continued ...
Страница 43: ...43 Figure 28B Schematic Wiring Diagram Burner Options VII ELECTRICAL continued ...
Страница 44: ...44 Figure 28C Ladder Diagram VII ELECTRICAL continued ...
Страница 70: ...70 Bare Boiler Assembly XIV Repair Parts continued ...
Страница 72: ...72 Jacket Assembly XIV Repair Parts continued ...
Страница 74: ...74 MPO IQ84 Thru MPO IQ231 Water Boilers Trim and Controls XIV Repair Parts continued ...
Страница 78: ...78 Beckett AFG Burner XIV Repair Parts continued ...
Страница 80: ...80 Beckett NX Burner XIV Repair Parts continued ...
Страница 92: ...92 U S Boiler Company Inc P O Box 3020 Lancaster PA 17604 1 888 432 8887 www usboiler net ...