12' Skew Bed Installation
TGW Systems' dedicated 12' skew bed typically is installed as the first 12' bed section in a NBC
conveyor line, starting from the charge end. The rollers are factory skewed to the requested side and
the installation is the same as any other NBC intermediate bed section.
A 12' wheeled guardrail is included to prevent the stalling of product as it is forced against the side
channel by the skewed rollers. The wheeled guardrail is shipped loose and must be field installed. To
install, line up the bolt holes on the guard with the holes in the top flange of the 12' skew bed side
channel. The end of the guard and the end of the
conveyor bed should be in line.