Performance Verification
46
GTS1063 and GTS1250 GBIC Test Systems Instruction Manual
Setup For PV
1. The GTS1250 and the test equipment should be warmed up for 20 minutes at
an ambient temperature between 20 and 30
_
C.
2. Calibrate the loop gain and offset of both sampling head channels. See your
oscilloscope and sampling head user manuals for more information.
3. When inputs or outputs of the GBIC Test System are not in use, replace the
50
W
terminations.
Tx DATA, CLOCK, and SYNC Output levels
Equipment
required
One sampling oscilloscope with SD22 sampling head
Two Semi-rigid cables for SD22 sampling head
One coaxial cable
One optical cable
GBIC, 1.25 GB/s
Power splitter
Prerequisites
See page 43
NOTE
. Make sure that the optical connector ends of both the fiber and the input
to the GTS1250 are well cleaned before performing this step.
1. Connect your wrist strap to the antistatic connector on the front of your
oscilloscope.
NOTE
. The longer wavelengths of 1310 nm and especially 1550 nm are sensitive
to loss in fiber due to bending of the fiber. The fiber bend radius of the GTS1250
fiber input should lay with >1.5 inch bend radius along the fiber’s entire length.
This precaution must be maintained throughout the entire performance
verification procedure.
2. Connect the optical fiber between the Tx and Rx connectors of the GBIC.
3. Connect an SMA cable between the Sync output of the GBIC Test System
and the oscilloscope Ext trigger input as shown in Figure 17.