GTS1063 and GTS1250 GBIC Test Systems Instruction Manual
43
Performance Verification
Use the following procedures to verify the warranted specifications of the GBIC
Test System. Before beginning these procedures, see page 45; photocopy the test
record and use it to record the performance test results. The recommended
calibration interval is one year.
These procedures test the following specifications:
H
Tx DATA, CLK, and SYNC voltage swing
H
Rx recovered DATA and CLK voltage swing
H
Tx DATA duty cycle
H
Random and deterministic jitter
H
GBIC PORT V
dd
Voltage Tolerance
Prerequisites
The tests in this section comprise an extensive, valid confirmation of perfor-
mance and functionality when the following requirements are met:
H
The cabinet must be installed on the GBIC Test System.
H
The GBIC Test System outputs must be terminated in a load of 50
"
2
W
.
H
The GBIC Test System must have been last calibrated/adjusted at an ambient
temperature b20
_
C and +30
_
C, must have been operating for a
warm-up period of at least 20 minutes, and must be operating in an
environment with temperature, altitude, humidity, and vibration within the
operating limits described in Environmental Specifications on page 37.