19 COMMISSIONING
On completion of the installation the lift is ready to be tested. The test must be carried out
according to the 'Midilift SL Certificate of Test and Installation' procedure. The lift can only be
commissioned once this has been correctly completed.
Adjust the over pressure switch to stop the lift with rated load and a max. of 75kg overload.
Before handing the lift over to the customer, ensure the work place is tidy and the lift is clean.
When handing the lift over to the customer or the person responsible for the lift, the following
must be demonstrated to him/her:
i. Full operation of the lift controls.
ii. The position and operation of all safety edges and surfaces.
iii. The lift manual lowering procedure and the passenger release procedure.
iv. Ensure the customer is aware of who to contact in case of a break down.
Before leaving the site you must ensure the customer has run through a complete operation
and is completely satisfied with the product.