Start--up procedures
93
851--164300 / C
Figure 33 Mains
connection to the
motor
230 Vac
380 / 440 Vac
3
Set the hoisting/lowering switch
S302
to
Lower
.
4
Check the training direction of the hoisting/lowering motor
by briefly pressing the hand crank safety switch
S303
.
5
If the transducer shaft was hoisted, perform the following
procedure:
a
Disconnect the ship’s 3-phase mains fuses
b
Change two of the connections to the terminals on the
motor overload switch
S301
.
c
Reinsert the 3-phase mains fuses in the ship’s fusebox.
6
Set the hoisting/lowering switch
S302
to
Stop
.
7
Put the the hand crank back to its storage position in the
Motor Control Unit.
8
Check if there is sufficient space under the keel to lower the
transducer.
9
Make sure that the flexible transducer cable is in such a
position that the transducer can be lowered without
stretching or hard-bending the cable.
Note
Watch this carefully during the next steps in this procedure!
10
Set the hoisting/lowering switch
S302
to the
Lower
position
to completely lower of the transducer.
- Lowering will be stopped automatically when the top of
the transducer shaft makes contact with the lower limit
switch
S305
.
Содержание SH80 - REV C
Страница 2: ......
Страница 14: ...Simrad SH80 X 851 164300 C Blank page...
Страница 61: ...Transceiver unit 45 851 164300 C Figure 13 Mounting the Transceiver Unit CD3110A...
Страница 186: ...Simrad SH80 170 851 164300 C 12 3 Installation drawings The SH80 installation drawings are provided on the next pages...
Страница 195: ...Installation remarks 179 851 164300 C Party Date Signature Party Date Signature Party Date Signature...
Страница 196: ...Notes...
Страница 197: ...Notes...
Страница 200: ......