Machine Operation
SY26U Excavator OMM
4-50
Operation and Maintenance Manual — 1119
SANY
When loading the excavator with work equipment
installed, place the work equipment in the front and travel
forward.
When loading the excavator without equipment installed,
travel in reverse up the ramps. Set the ramps at no more of
an angle than 15° (1).
Use the following procedures during loading:
1. Align the centerline of the machine with that of the
trailer.
2. Slowly drive the machine up the ramps.
3. When the machine tilts toward the trailer side, lower
the bucket close to the trailer floor. Drive slowly until
the tracks are completely on the trailer.
4. Slightly raise the bucket. Retract the arm and keep it in
a lower position. Slowly swing the upper structure
180°. Lower the dozer blade.
5. Fully curl the bucket and arm. Slowly lower the boom.
Fig. 4-69
0002937
Fig. 4-70
0002939
1
Fig. 4-71
0002941