![Santerno SUNWAY TG1200 1000V TE OD Скачать руководство пользователя страница 58](http://html1.mh-extra.com/html/santerno/sunway-tg1200-1000v-te-od/sunway-tg1200-1000v-te-od_installation-manual_810313058.webp)
MODULAR SUNWAY TG
TE OD
INSTALLATION GUIDE
58/
139
Rev. 03
– 01/06//2018
Floating field
Earthed field
Single converter, single master
1
1
1
Dual converter, multi-master
2
1
(1)
or 2
2
(1) Optional single secondary compatibility required
6.5.
Power supply connection
For the technical data concerning the number of connectable cables, the maximum allowable cable cross-
section and cable lug type, please refer to section 12.7.2.
Figure 30: Location of the auxiliary power supply terminal board
The terminal board for the power supply cable connection is X10 in the AC section (Figure 30).