80
SPARC M5-32 and SPARC M6-32 Servers Installation Guide • December 2014
1. Plan and prepare the entire route to the installation site.
Walk the entire route and note any obstacles that must be avoided. Ensure that all
floors along the route can support the full weight of the server.
Cover raised data center flooring with fiberboard to protect it, prepare a metal
sheet to cross any gaps in the floor (for example, when entering an elevator), and
prepare a metal ramp to go up or down minor floor elevations.
For more information, see:
■
“Access Route Guidelines” on page 55
■
“Use a Metal Plate to Cross Gaps in the Floor” on page 82
■
“Move Server Up or Down a Ramp” on page 84
2. Ensure that the server doors are closed and secured.
Alternatively, remove both doors and take them separately to the installation site.
For instructions on removing a door, see
3. Ensure that all four leveling feet on the bottom of the server are raised and out
of the way.
See
“Raise the Leveling Feet” on page 89
for instructions.
4. Using four or more people, push the server to the installation site.
Always push the server along its edges. Move the server slowly, at approximately
two feet per second (0.65 meters per second) or slower. Position people at each
corner of the server to help guide it.
For extra leverage, remove the rear door and push the server on either side of the
rear LED panel. For instructions of removing the door, see
Содержание sparc M5-32
Страница 1: ...SPARC M5 32 and SPARC M6 32 Servers Installation Guide Part No E41215 05 December 2014 ...
Страница 8: ...viii SPARC M5 32 and SPARC M6 32 Servers Installation Guide December 2014 ...
Страница 16: ...6 SPARC M5 32 and SPARC M6 32 Servers Installation Guide December 2014 Front Components ...
Страница 18: ...8 SPARC M5 32 and SPARC M6 32 Servers Installation Guide December 2014 Rear Components ...
Страница 21: ...Understanding the Server 11 FIGURE DCU Locations Rear of Server ...
Страница 43: ...Preparing the Site 33 FIGURE 4 Wire Power Cord AC Plug 460P9W Figure Legend 1 L1 2 L2 3 L3 4 Ground ...
Страница 51: ...Preparing the Site 41 ...
Страница 82: ...72 SPARC M5 32 and SPARC M6 32 Servers Installation Guide December 2014 ...
Страница 106: ...96 SPARC M5 32 and SPARC M6 32 Servers Installation Guide December 2014 ...
Страница 182: ...172 SPARC M5 32 and SPARC M6 32 Servers Installation Guide December 2014 ...