GATE SYSTEM INSTALLATION PROCEDURE
Printed:
10/23/2019
15-1507
OHI
OBERMEYER Hydro Inc.
14 of
36
9.
Apply spray foam into the air block out (50% full)
Figure 7: Description of step 9
10.
Visually inspect air connection once more to assure all
connections are tight and no leaks can occur. Fold the bladder back
over so that all large bladder holes go over anchor bolts. Carefully
inspect that the hose is falling into the air blockout as bladder is
unfolded back into position.
11.
Repeat steps 1 through 10 on the remaining bladders.
4.
POSITIONING OF GATES
Figure 6: Description of steps 4 through 8