GATE SYSTEM INSTALLATION PROCEDURE
Printed:
10/23/2019
15-1507
OHI
OBERMEYER Hydro Inc.
27 of
36
5.
Loosen the nuts to release the bottom interpanel seal retainers and
nearest hinge retainers that interfere with placement of the EPDM
sheet. Remove these retainers and set aside.
6.
Starting with the spillway under the bladder, coat every surface of
the bladder and spillway that will come into contact with the
EPDM sheet.
7.
Replace EPDM sheet in the proper position shown in figure 20
with all holes over their respective studs.
8.
Replace all retainers that were removed for EPDM placement, and
re-torque all nuts to their required value.
Holes cut in figure 19 (step
1) are located here
Second holes for main
anchors will be cut here
Holes for hinge studs and
interpanel seal studs will be cut
here
Figure 20: Top view of EPDM with all holes shown