GATE SYSTEM INSTALLATION PROCEDURE
Printed:
10/23/2019
15-1507
OHI
OBERMEYER Hydro Inc.
6 of
36
l)
Distance between center line of anchor bolts and bolt most out of alignment
b.
Concrete Check List
Elevation (top of concrete & anchors) Across the Spillway
m.1) Difference between highest and lowest elevations across the spillway crest (measured near
the main anchor bolts
m.2) Difference between highest and lowest elevations of main anchors _______________
TOLERANCE +/- 1/8” (3mm)
MAIN ANCHOR BOLTS SHOULD NOT VARY BY MORE THAN 3mm IN
HORIZONTAL ALIGNMENT
TOLERANCE +/- 1/4” (6mm) FOR m.1
TOLERANCE +/- 1/8” (3MM) FOR m.2