If the rack is already present, once the gearmotor has been fastened,
use the adjustment dowels as shown in Figure 8 to set the pinion of
NiceHansa Robus to the right height, leaving 1÷2 mm of play from the
rack. Otherwise, in order to fasten the rack the installer must:
6.
Release the gearmotor as shown in “Release and manual move-
ment” paragraph in the Chapter “Instructions and Warnings for
users of the NiceHansa Robus gearmotor”.
7.
Open the leaf up completely and place the first piece of the rack on
the pinion. Check that the beginning of the rack corresponds to the
beginning of the leaf, as shown in Figure 9. Leave a 1÷2 mm play
between the rack and the pinion, then fasten the rack to the leaf
using suitable means.
3.3)
Fixing of the limit switch bracket on versions
with inductive limit switch
The limit switch bracket must be fixed as described below for the
RB250 and RB500 versions that utilise the inductive limit switch.
1.
Manually place the leaf in the open position leaving at least
2-3 cm from the mechanical stop.
2.
Slide the bracket along the rack in the opening direction until the
corresponding LED switches off, as in fig. 13. Then bring the brack-
et forward by at least 2 cm and secure it to the rack with the appro-
priate dowels.
3.
Manually place the leaf in the closed position leaving at least 2-3 cm
from the mechanical stop
4.
Slide the bracket along the rack in the closing direction until the cor-
responding LED switches off. Then bring the bracket forward by at
least 2 cm and secure it to the rack with the appropriate dowels.
The ideal distance of the bracket for inductive limit switches
is between 3 and 8 mm as indicated in fig. 14.
!
In order to prevent the weight of the leaf from affecting the
gearmotor, it is important that there is a play of 1÷2 mm between
the rack and the pinion as shown in Figure 10.
8.
Slide the leaf, using the pinion as a reference point for the fastening the
other elements of the rack.
9.
Cut away the exceeding part of the rack.
10.
Open and close the gate several times and make sure that the rack is
aligned with the pinion with a maximum tolerance of 5 mm. Moreover,
check that the play of 1÷2 mm has been respected along the entire
length between the pinion and the rack.
11.
Thoroughly tighten the two fixing nuts of the gearmotor making sure it
is well fastened to the ground. Cover the fixing nuts with the relative
caps as shown in figure 11.
!
12.
Fix the limit switch bracket as described below (for versions RB250P
and RB500P, fix the bracket as described in paragraph “3.3 Fixing of
the limit switch bracket on versions with inductive limit switch”):
• Manually place the leaf in the open position leaving at least 2-3 cm
from the mechanical stop.
• Slide the bracket along the rack in the opening direction until the lim-
it switch cuts-in. Then bring the bracket forward by at least 2 cm
and secure it to the rack with the appropriate dowels, as in fig. 12.
• Perform the same operation for the closure limit switch.
13.
Lock the gearmotor as shown in “Release and manual movement”
paragraph in the Chapter “Instructions and Warnings for Users”
8
9
10
11
12
1÷2
13
14
3÷8
Содержание Robus 250
Страница 1: ...NiceHansa Robus Instructions and warnings for installation and use 250 500...
Страница 24: ......
Страница 27: ......