101
Programs
Leica TPS800-4.0.0en
4
Select sub application Check, Stake, Check
Slope or Stake Slope:
4a Sub application Check
The sub application
Check
is used for as-built
checks. The points can be measured or selected
from the memory. As result you will get Chainage
and Offset values relative to an existing horizontal
alignment and the Height difference relative to a
vertical alignment or manually entered height.
)
Defined Chainage and Increment values will
not be considered in the Check mode.
P1 Target point
P2 Target point
a
Horizontal alignment
b
Chainage
c
Offset, is positive on the right hand side of the
alignment.
d
Height difference, is positive when target point is
higher than the alignment.
PtID :
A3
hr : 1.500
M
Offset :
Left
Chainage :
90.194 m
Offset :
4.678
m
Ht.Diff. :
0.348 m
IR
I
ALL
DIST
REC
3D-Road CHECK 1/2
TPS800_Z116
a
P1
P2
c+
d+
b
c-
d-
P0