The actual installation location may be determined after review of many factors, some of which are outlined below:
Circuit Breaker Cabinet Mounting
Pros
Cons
Readily accessible to Maintenance personnel.
Trip initiate signal may not be available should
it be the desired interface for the Aux A input
assertion.
A 52 / a contact (in the actual trip circuit or
individually wetted) for asserting the Aux A input,
and a 52 / b contact (in the actual green light circuit
or individually wetted) signal for asserting the Aux
B input are readily available. A trip initiate signal
may also be available for the Aux A input assertion if
desired.
May be environmentally unfriendly (temperature,
humidity, electrical noise, transients) for both the
equipment and personnel.
Secondary current circuit interface is readily
available (from bushing CTs).
Integration may be more difficult (long distances,
electrical noise, step potential).
Table 2A: Breaker Cabinet Installation Considerations
Control House Mounting
Pros
Cons
Centralized location for multiple unit installations.
May lie within an area not readily accessible to
Maintenance personnel.
Trip Initiates (red light) signal for asserting the Aux
A input, and an end of mechanism travel (green
light) signal for asserting the Aux B interfaces are
readily available. A 52 / a contact signal may also
be available for the Aux A input assertion if desired.
The 52/a and 52/b may not be available if they
are the desired interface for the Aux A and Aux
B input assertion.
Secondary current circuit interface is readily
available (from relays).
Usually easier to integrate (short physical wiring
runs in close proximity to an RTU, PLC, substation
computer, modem, port switcher, etc.).
Not near SF
6
ports on circuit breaker, long cable
runs from sensors may increase noise.
Environmentally friendly (temperature, humidity,
electrical noise, transients) for both the equipment
and personnel.
Table 2B: Control House Installation Considerations