COMMISSIONING / START-UP PROCEDURE
1. Check that all the necessary connections have been correctly made.
2. Ensure that the Compressed Air / Oil Separator Tank and pump gearbox are filled with the
correct oil type and quantity.
3. Prime and Run the water pump at 125 PSI [0.86 MPa] with compressor engaged.
4. Run the compressor for 30 seconds to allow oil to circulate.
5. Stop unit and check compressor oil level – top up if necessary.
6. Turn the bypass valve on the Foam unit pump to “bypass” and provide a suitable receptacle to
collect the foam agent.
7. Ensure that there is sufficient foam agent in the tank(s). For
Foam unit 3.3/5.0/6.5
select tank
A
8. Select simulated flow on the UV display by pressing the Menu button then pressing the
“Simulated Water” button on the screen or button. Then return to the operating screen by
selecting the “Return to Operation” button.
9. Press the
button on the control head, and the Foam unit pump will prime itself. The pump
will run for 30 seconds or until prime is achieved. If no prime is made, the display will show a
plain test warning. Repeat this step once more to attempt to prime the pump.
If priming is not achieved after several attempts, Insure the foam supply is connected and
available to the pump.
10.
For 3.3/5.0/6.5 Foam unit
, flush then select tank
B
, and repeat the priming procedure for that
tank.
11. When prime is achieved, deselect simulated flow by return to the menu and turning off simulated
flow.
12. Return the bypass valve to the inject position.
The unit is now ready to run.