8. Initial start-up
Danger due to incorrect operation!
Commissioning may only be carried out by
qualified personnel (electricians or specialists
with equivalent training)..
Risk of electrical shock!
Hazardous electrical voltage!
Follow safety instructions for work on live
components.
Remove the elongated transport locks from
the flow tubes (Fl01-Fl03).
Do not connect the permeate line to the
expansion vessel until all other commission-
ing steps (especially flushing of the mem-
branes) have been carried out.
At the beginning of each commissioning with
the use of new membrane(s), the ROL unit
produces a higher permeate quantity in the
first 2-4 hours, which is combined with a
higher conductivity.
The pump may only be operated with the
water inlet valve open, otherwise it could be
damaged. Exception: initial start-up.
Operation steps in the short overview:
Step 1:
Check mechanical integrity, water
connection and cabling
Step 2:
Removal of the transport lock from
the flow tubes (Fl01-Fl03)
Step 3:
Flushing the membranes
Step 4:
Adjustment of recovery value
Step 5
: Connect the permeate pipe to the
extension vessel and thus also to the con-
sumer
(It is important that this step is only
done at the very end of the commission-
ing process)
Step 6:
Filling the anti-calcant canister and
adjusting the dosing pump
.
Step 7:
Observe device and check for leaks,
eliminate leaks if necessary.
Содержание WL-ROL 160-1200 Series
Страница 1: ...FlexLine Reverse osmosis plants MANUAL WLROL EN E 8881184 WLROL ENj WL ROL 160 1200...
Страница 62: ...Page 62...
Страница 65: ...Page 65 13 Declaration of Conformity...
Страница 66: ...Page 66...
Страница 72: ...Page 72 This page intentionally left blank...
Страница 73: ...SPA Page 73 This page intentionally left blank...