Figure 5-33
Using a buckle to secure the AC power cable
2.
Open the buckle, as shown in step 2 of
.
3.
Lock the buckle to the joint between the AC power cable and socket and secure the AC
power cable to the socket, as shown in step 3 of
.
NOTE
Before fully closing the buckle, slide the buckle to a proper position where the power cable can be
tightly secured.
4.
for other power cables.
Step 3
Route and bundle cables.
NOTE
For details on how to route and bundle cables, see
12 General Cable Routing Description
Cable Routing and Bundling Technology
.
----End
5.23 Powering On the N8500
This section explains how to power on the N8500 after it is installed and cabled.
Prerequisites
l
All components have been correctly installed and cabled.
l
The switch of the PDU or PDB has been turned off.
l
The power voltage conforms to device requirements.
Context
Before powering on the N8500, observe the following precautions:
OceanStor N8500 Clustered NAS Storage System
Installation Guide (for T Series V100R005)
5 N8500 Installation (with the S2600T Storage System as the
Storage Unit)
Issue 02 (2015-09-22)
Huawei Proprietary and Confidential
Copyright © Huawei Technologies Co., Ltd.
84