6. If possible, disconnect all loads connected downstream
of the measured point, as the impedance of these users
could distort the test results. Perform the preliminary
calibration of the test leads as described in § 6.4.2
Connect the shuko plug, the alligator clips or the
remote lead to the electrical mains according to Fig. 18,
Fig. 19, Fig. 20 and Fig. 22.
Note the presence of the correct voltage values
between L-L and L-PE corresponding to the selections
carried out in the initial phase (see § 5.1.4) as shown in
the screen to the side
7. Press the
GO/STOP
key
for few seconds
or the
START
key on the remote lead. During this whole
stage, do not disconnect the measuring leads of the
instrument from the system under test.
In case of positive result (three-phase short-circuit
current for the L-L case in the image supported by the
cable with the performed selections), the screen to the
side is displayed by the instrument.
Press the
SAVE
button or touch the
icon to save
the measurement (see § 7.1).
8. In case of negative result (three-phase Isc current for
the L-L case in the image NOT supported by the cable
with the performed selections), the screen to the side is
displayed by the instrument.
Note the presence of the measurement result
highlighted in red.
Press the
SAVE
button or touch the
icon to save
the measurement (see § 7.1).