11
Commissioning
Technical requirements
All components to be monitored must be connected and operating.
The visual display and operating panel must be provided with a CompactFlash™ card and the power
supply must be switched on.
Startup behaviour
To commission the display and operating panel, switch on the power supply. First a system test is car-
ried out and operating system WinCE with the relevant drivers boots up.
After that the user program is automatically loaded from the CompactFlash™ and the start menu
“Overview” is displayed (duration approx. 1 min.).
Note
Any fault occurring during start-up will be indicated on the display.
Shutdown behaviour
As short power supply failure of up to 10 ms will be buffered by the power supply unit. In the event of a
longer power failure you have to restart SPECTOR
control
in order to restore the power supply.
Factory settings
The graphical screen masks are configured by GESTRA. All adjustable masks are completely available,
no matter whether the indicated instruments are part of the bus system or not. Subsequent expansion
or modification is therefore possible at any time.
The scope of the adjusted values and hence the degree of preadjustments depends on whether a
preconfigured OEM version is used or whether SPECTOR
control
will be connected to an existing bus
system and therefore the configuration of the system must be completely new.
If a preconfigured OEM version is used, the built-in components with the adjusted parameters are
stored on the CompactFlash™ card.