22
System Control
Sequence of setup
Before starting the set-up procedure, make sure that all devices are interconnected via CAN bus. The
CANopen protocol is used for the data exchange between the equipment groups.
To be able to access the CANopen equipment of the plant you must first check and, if necessary, modify
the basic settings.
Preconfigured installations will be completely parametrised by GESTRA. The data is stored on the Com-
pactFlash™ card. Modifications are therefore not necessary.
For a subsequent installation or expansion of SPECTOR
control
follow the configuration steps described
below.
Note
Any modification of the basic settings has a direct effect on the boiler monitoring system
and the operation functions.
We recommend the following configuration sequence:
1. Check/configure system settings
2. Check/configure connected CANopen equipment
3. Check/configure connected analogue equipment (I/O module)
4. Check/configure connected digital equipment (I/O module)
5. Check/configure controller
6. Check/configure boiler parameters
7. Check/configure burner parameters
8. After finishing the configuration, restart the system
(switch power supply off and on)
(Only applicable if settings of CANopen equipment – cf. item 2 – were modified)
Note
SPECTOR
control
does not have its own on/off switch.
To turn off, disconnect the power supply in the control cabinet or directly at the equip-
ment by unplugging the mains plug (24 V DC).