The
OPEN POLE REM CURR PKP
setting specifies pickup level for the remote-end current estimated by the relay as the local
current compensated by the calculated charging current. The latter is calculated based on the local voltages and the capac-
itive reactances of the line. This setting is relevant if open pole condition at the remote end of the line is to be sensed and
utilized by the relay (
OPEN POLE REM OP
FlexLogic operand).
The
OPEN POLE MODE
setting selects the mode of operation of the open pole function. When the “Accelerated” mode is cho-
sen, an open pole will be declared ½ cycle after trip output operation and before the breaker pole opens. This blocks dis-
tance loops involved in the faulted phase and phase selector, and arms the trip output to produce three-pole trip for the next
fault. If the fault evolves into multi-phase fault before breaker pole opens for the first fault, the remaining in-service distance
loops would initiate a three-pole trip. When the “Traditional” mode is selected, then an open pole is declared only after the
breaker opens and current disappears. If the fault evolves into a multi-phase fault before the circuit breaker pole opens for
the first fault, the phase selector will change the fault type from a single-line-to-ground fault to a multi-phase fault, thereby
initiating a three-pole trip.
The
OPEN POLE DETECTION
setting selects the signals used to detect an open pole condition. When “I AND V AND CBaux”
value is selected, the breaker 52 contacts and the current with optional voltage signals are used to determine open pole
conditions. For the “I AND V only” selection, only the current with optional voltage signals are used.
For convenience, the position of the breaker poles defined in the breaker control feature and available as FlexLogic oper-
and
BREAKER 1
Φ
A CLSD
through
BREAKER 1
Φ
C CLSD
and
BREAKER 1 OOS
are used by the open pole feature if the “I AND
V AND CBaux” detection value is selected.
For correct operation of the open pole detector, the breaker control, trip output, and single-pole autoreclose features must
be enabled and configured properly. When used in configuration with only one breaker, the
BREAKER 2 FUNCTION
should be
“Enabled” and the
BREAKER 2 OUT OF SV
setting should be “On” (refer to the
Breaker Control
section earlier in this chapter
for additional details).
Содержание L60
Страница 10: ...x L60 Line Phase Comparison System GE Multilin TABLE OF CONTENTS ...
Страница 57: ...GE Multilin L60 Line Phase Comparison System 2 27 2 PRODUCT DESCRIPTION 2 3 SPECIFICATIONS 2 ...
Страница 58: ...2 28 L60 Line Phase Comparison System GE Multilin 2 3 SPECIFICATIONS 2 PRODUCT DESCRIPTION 2 ...
Страница 100: ...3 42 L60 Line Phase Comparison System GE Multilin 3 3 DIRECT INPUT AND OUTPUT COMMUNICATIONS 3 HARDWARE 3 ...
Страница 482: ...6 26 L60 Line Phase Comparison System GE Multilin 6 5 PRODUCT INFORMATION 6 ACTUAL VALUES 6 ...
Страница 554: ...10 8 L60 Line Phase Comparison System GE Multilin 10 2 BATTERIES 10 MAINTENANCE 10 ...
Страница 674: ...B 110 L60 Line Phase Comparison System GE Multilin B 4 MEMORY MAPPING APPENDIX B B ...
Страница 704: ...C 30 L60 Line Phase Comparison System GE Multilin C 7 LOGICAL NODES APPENDIX C C ...
Страница 720: ...E 10 L60 Line Phase Comparison System GE Multilin E 1 PROTOCOL APPENDIX E E ...
Страница 732: ...F 12 L60 Line Phase Comparison System GE Multilin F 2 DNP POINT LISTS APPENDIX F F ...
Страница 742: ...H 8 L60 Line Phase Comparison System GE Multilin H 3 WARRANTY APPENDIX H H ...