3. Visually inspect the small packages and the sample probe to ensure that no major
damage has occurred. If damage has occurred, contact the shipping company and
Galvanic Applied Sciences. Place the small packages and the sample probe aside in
a safe, secure storage area as they are not needed at this stage of the system
installation.
The analyzer weighs approximately 275 lb (125 kg). Use suitable precautions
when removing it from the crate and placing it in the facility.
4. Locate and remove the four (4) bolts that secure the analyzer framework to the 2' x 4'
boards at the bottom of the shipping crate.
5. Once the bolts are removed the analyzer system can be lifted from the crate.
6. Lay the analyzer system frame onto a structurally strong and level surface and inspect
for any visual damage.
7. Remove the plastic wrap from the analyzer system to gain access to the doors of the
cabinets.
8. Open the cabinet doors and
carefully
remove the packing material from inside each of
the two (2) analyzer cabinets.
Care should be taken while removing the cabinet packing material so that
no hardware or wiring is damaged.
9. Inspect the internal equipment to ensure that no damage has occurred and that no
components have become loose during transport.
If any damage is visible contact Galvanic Applied Sciences Inc. immediately
and do not proceed with the system installation. Do not attempt to facilitate
repairs yourself as this will negate and/or invalidate any possible insurance
claim or equipment warranty
.
10. If no damage is apparent, the analyzer system is ready for transport to the installation
(sample point) site. The analyzer system framework has two (2) lifting rings located at
the top. Installation of proper clevises is recommended. The lifting rings are rated for
approximately 227 kg / 500 lbs per ring.
2.4
Installation Procedure
The installation procedure of the 943-TGX-CE analyzer system consists of the following steps
1. Mounting of the Analyzer System (Section 2.4.1)
2. Mating of the Process and Analyzer System Flanges (Section 2.4.2)
3. Connection of the AC Power Service (Section 2.4.3)
4. Connection of the Analog Signal Cables (Section 2.4.4)
5. Connection of the Digital Signal Cables (Section 2.4.5)
6. Connection of the Instrument Air Services (Section 2.4.6)
7. Connection of Steam (Section 2.4.7)
Содержание 943-TGX-CE
Страница 132: ...Revision 4 132 April 2020 Figure 81 Oven Cabinet Door Removed ...
Страница 133: ...Revision 4 133 April 2020 Figure 82 Control Cabinet Door Removed ...
Страница 134: ...Revision 4 134 April 2020 Figure 83 Power Steam Air Signals Connection Details ...
Страница 135: ...Revision 4 135 April 2020 Figure 84 AC Wiring Schematic ...
Страница 136: ...Revision 4 136 April 2020 Figure 85 DC Signals and Wiring Diagram ...
Страница 137: ...Revision 4 137 April 2020 Figure 86 Flow Diagram ...