43
ED250
08-2018
DL4614-070
dormakaba ED250 IG Installation Instructions
Chapter 16
Fig. 16.2.1 End view, strike side
Fig. 16.2.2 End view, door pivot side (offset pivot door)
4 7/8”
Top of finished floor
5 1/2”
min.
Blockout
Cement
case cover
16.1 Verify concrete floor blockout
16 In-ground case installation
Fig. 16.1.1 Minimum blockout dimensions
16.1.1 Verify blockout for ED250 in ground case.
Using applicable ED250 in-ground installation template
(Chapter 13) to verify:
1. Concrete floor blockout dimensions. Reference
Fig. 16.1.1 for minimum blockout dimensions.
2. Blockout location referencing door jambs.
3. Cement case orientation in blockout. Electrical wiring
at end of case opposite pivot (double doors, center
of blockout).
16.2 Install cement case, single door
16.2.1 Set cement case into blockout
NOTICE
Reference applicable installation template
(Chapter 13) and contractor and/or architect
documentation to position cement case
spindle in blockout.
WARNING
Hand pinch point and crushing hazards!
1. Lower cement case into blockout and shim case into
position.
7 1/2” min.
pit width
5 1/2” min. pit
depth
Min. pit length:
refer to installation
template
Bottom of blockout
4 7/8”
Top of finished floor
Cement case cover
5 1/2”
min.
Jamb
NOTICE
Installation site may require modification of
steps referenced in Chapter 16.