3.2.1.1 Installation of the Protection Cover for Piping
1. Take a snap bushing and install it on Cover-5 as shown in
Figure 3-11
.
(Figure 3-11: Install the Snap Bushing)
2. Take Cover-5 and install it at where
Figure 3-11-1
indicates. Please use 7 pieces M4*L10
screws for the installation.
(Figure 3-11-1: Install the Protection Cover)
NOTE:
Support the top pipeline. The configuration of the pipe, valves, and filters must be
identical to that of the bottom pipeline.
3.2.2 Condenser Drain Connection
Gravity drainage (drainage from bottom only):
The gravity water pipe has been connected to the lower part of the cabinet at one end with
an additional 3.94 ft. of length remaining. The drain pipe must be insulated and pass the
other end through the reserved hole at the bottom to drain the condensed water. The
condensed water is drained by making use of the height difference of the unit. Make sure
the horizontal slope between the two ends of the pipe is at least 5 degrees.
Содержание InfraSuite RDA037
Страница 11: ...11 Unit inch Figure 2 4 Outdoor Unit Appearance and Dimensions...
Страница 63: ...63 5 5 2 Data History Path Main Page Measurement Data History...
Страница 64: ...InfraSuite R Series Air Cooled Type 64 5 5 3 Warning Path Main Page Maintenance Warning...
Страница 65: ...65 5 5 4 Historical Event Path Main Page Maintenance Historical Event...
Страница 88: ......
Страница 89: ......
Страница 90: ......
Страница 92: ...5013295900...