No. Work to be undertaken for commissioning
Attachment / Measured
values
1
Filling the heating system with water and checking the water pressure
2
Fill the siphon with water
3
Vent the air in the heating system
4
Checking the water-side connections for tightness
5
Checking the type of gas supplied. Checking that the boiler is suitable for the gas supplie
d?
6
Checking the gas supply pressure
7
Checking the capacity of the gas meter
8
Checking the tightness of the connections and the gas pipes
9
Purge the gas supply pipe of the boiler
10
Checking the electrical connections
11
Checking the air supply connections and flue gas discharge connections
12
Checking the functioning and operational status of the boiler
13
Checking the air/gas ratio
14
Remove the measuring device and close the measurement points
15
Correctly fit the front housing of the boiler
16
Attaching the Gas Type sticker
17
Set the room thermostat or the regulator
18
Instruct the user and hand over the necessary documents
19
Fill in the warranty card together with the user
20
Confirmation of commissioning
Date
(dd-mm-yy)
Company name, signature of engineer
10.1 Checklist for commissioning
10. Checklists
Содержание MCA Pro 115
Страница 45: ...45 MCA Pro 45 65 90 115 MCA Pro ISM Rv 4 1 2 2017 4 Installation H D G C B A E I J F ...
Страница 117: ......
Страница 118: ......
Страница 119: ......