Figure 3.25: Mounting of bottom plate, E1 enclosure.
The bottom plate of the E1 enclosure can be mounted from either in or outside of the enclosure, allowing flexibility in the installation process, i.e. if
mounted from the bottom, the connectors and cables can be mounted before the adjustable frequency drive is placed on the pedestal.
3.3.9 IP21 Drip shield installation (D1 and D2 enclosure)
To comply with the IP21 rating, a separate drip shield is to be
installed as explained below:
•
Remove the two front screws.
•
Insert the drip shield and replace the screws.
•
Torque the screws to 5.6 Nm (50 in-lbs).
Figure 3.26: Install the drip shield.
VLT
®
Automation Drive FC 300
Instruction Manual High Power
3 How to Install
MG.33.U2.22 - VLT
®
is a registered Danfoss trademark
3-27
3