Figure 3.2: Mounting Template
3.2.4 Lifting
Always lift the adjustable frequency drive using the dedicated lifting holes. For all D and E2 (IP00) enclosures, use a bar to avoid bending the lifting holes
of the adjustable frequency drive.
Figure 3.3: Recommended lifting method, D and E enclosures
NOTE!
The lifting bar must be able to handle the weight of the adjustable frequency drive. See
Mechanical Dimensions
for the weight of the
different enclosures. Maximum diameter for bar is 1 inch (25 cm). The angle from the top of the drive to the lifting cable should be 60
degrees or greater.