Si18-201
Troubleshooting - Outdoor Unit Related
Service Diagnosis
303
3.4.6
Power Transistor Check
(
Capacitor Voltage Check
)
Check No.6
Power Transistor Check
"
Do not touch the charging unit for 10 minutes after turning the breaker off.
"
Even when touching the charging unit after 10 minutes, use a multiple meter to ensure that
the power supply voltage of power transistor is 50V or less.
"
Measure U,V,W either on terminals of control PC board on the substrate side or on the
compressor terminals.
"
Measure (+),(–) of the power transistor on (+) / (–) section of capacitor as shown in the figure
below.
∗
If the resistance value is not normal, replace the control PC board.
Capacitor Voltage Check
"
Follow the below figure to measure the capacitor voltage with breaker kept ON, while take
enough care not to touch the charging unit .
Negative (–) terminal of tester
(positive (+) terminal for digital
type)
(+) of power
transistor
UVW
(–) of power
transistor
UVW
Positive (+ terminal of tester
(negative (–) terminal for digital
type)
UVW
(+) of power
transistor
UVW
(–) of power
transistor
Normal resistance
∞
Several K
Ω
to
several M
Ω
Several K
Ω
to
several M
Ω
∞
Resistance for NG
0
0 to several
Ω
0 to several
Ω
0
Содержание FTX25JVEA9
Страница 9: ...Si18 201 viii Table of Contents...
Страница 71: ...Specifications Si18 201 58 Specifications...
Страница 206: ...Si18 201 Remote Controller Operations 193 1 1 2 FVX25 35KZ...
Страница 207: ...Remote Controller Si18 201 194 Operations 1 1 3 FTXD25 35KZ...
Страница 208: ...Si18 201 Remote Controller Operations 195 1 1 4 FTK FTX50 60H...
Страница 209: ...Remote Controller Si18 201 196 Operations 1 1 5 FTKD FTXD50 60 71J...
Страница 213: ...Remote Controller Si18 201 200 Operations 1 1 9 FHYC35 50 60 71K Optional Accessory BRC7C612WC...
Страница 214: ...Si18 201 Remote Controller Operations 201...
Страница 216: ...Si18 201 Remote Controller Operations 203...
Страница 217: ...Remote Controller Si18 201 204 Operations...
Страница 234: ...Si18 201 Method of Field Set Operating Test 221 2 3 Interface Adaptor for Room Airconditioner KRP928A1S...
Страница 237: ...Method of Field Set Si18 201 224 Operating Test...
Страница 262: ...Si18 201 Troubleshooting SkyAir Indoor Unit Service Diagnosis 249...
Страница 393: ...Wiring Diagrams Si18 201 380 Appendix FHYC35 50 60 71KVE9 3D005668C...
Страница 394: ...Si18 201 Wiring Diagrams Appendix 381 FHYC35 50 60 71KV1C9...
Страница 395: ...Wiring Diagrams Si18 201 382 Appendix FDYM60 03FAV1 FDYM60 03FAVAL C 3D019816D OPTION...
Страница 396: ...Si18 201 Wiring Diagrams Appendix 383 FDYM60 03FAV1C...