SiBE12-816_D
Trial Operation
Trial Operation and Field Settings
300
3. Trial Operation
3.1
RA Indoor Unit - F(C)TXG, FTXS, FVXS, FLK(X)S,
FDK(X)S Series
Outline
1. Measure the supply voltage and make sure that it falls in the specified range.
2. Trial operation should be carried out in either cooling or heating mode.
3. Carry out the trial operation in accordance with the operation manual to ensure that all
functions and parts, such as flap movement, are working properly.
The air conditioner requires a small amount of power in its standby mode. If the system is
not to be used for some time after installation, shut off the circuit breaker to eliminate
unnecessary power consumption.
If the circuit breaker trips to shut off the power to the air conditioner, the system backs up the
operation mode. The system then restarts operation with the previous mode when the circuit
breaker is restored.
In cooling mode, select the lowest programmable temperature; in heating mode, select the
highest programmable temperature.
Trial operation may be disabled in either mode depending on the room temperature.
After trial operation is complete, set the temperature to a normal level.
(26°C to 28°C in cooling mode, 20°C to 24°C in heating mode)
For protection, the system does not start for 3 minutes after it is turned off.
Detail
ARC466 Series
(1) Press the On/Off button to turn on the system.
(2) Press the center of the Temp button and the Mode button at the same time.
(3) Select “
T
” (trial operation) with the Temp
▲
or
▼
button.
(4) Press the Mode button to start the trial operation.
(5) Press the Mode button and select operation mode.
(6) Trial operation terminates in approx. 30 minutes and switches into normal mode. To quit a
trial operation, press the On/Off button.
(R11676)
(2) (4) (5)
(1) (6)
(2) (3)
(3)
Содержание 2MKS40G2V1B
Страница 12: ...SiBE12 816_D 1 List of Functions Part 1 List of Functions 1 Functions 2 1 1 Cooling Only 2 1 2 Heat Pump 5 ...
Страница 180: ...SA Indoor Unit FFQ Series SiBE12 816_D 169 Operation Manual 2 Start 5s 5s 5s 5s 5s End ...
Страница 290: ...Outdoor Unit SiBE12 816_D 279 Removal Procedure 15 Lift and remove the electrical box Step Procedure Points R12537 ...