C H A P T E R
1
Installation Roadmap
•
Installation Roadmap
The following table lists the tasks to install the Cisco NCS 6000 Fabric Card Chassis (FCC) and its components
and prepare the system for operation. Use this table as a checklist to ensure that all components are properly
installed in the correct order. For information about a step, see the respective section of this installation guide.
Table 2: Overview of Installation Steps
Check
See
Step
Cisco Network Convergence System 6000
Series Routers Unpacking, Moving, and
Securing Guide
1. Verify that the FCC is securely bolted to
the floor.
About the Power Enclosure, on page 13
section
2. Install the power enclosure.
Installing the Fabric Card Chassis Ground
Cable, on page 35
section
3. Ground the FCC.
Installing an AC or DC Power Tray, on page
18
section
4. Install the power trays.
Installing the Front Exterior Cosmetics, on
page 22
section
5. Install the external cosmetics on the front
of the FCC.
Installing the Rear Exterior Cosmetics, on
page 28
6. Install the external cosmetics on the rear
of the FCC.
Installing an AC or DC Power Module , on
page 46
section
7. Install power modules in the power trays.
Cisco Network Convergence System 6000 Fabric Card Chassis Hardware Installation Guide
1