Start up the heating system
Logano GE615 - We reserve the right to make any changes due to technical modifications.
42
5.1.1
Creating operating pressure (sealed
heating systems)
On sealed heating systems the pressure gauge marker
must be within the green field.
z
Set the red needle on the pressure gauge to the
required operating pressure (at least 1 bar pressure).
z
Only fill the system via a WRAS approved method.
z
Vent the heating system during filling.
Fig 58 Pressure gauge for sealed systems
1
Red needle
2
Pressure gauge needle
3
Green field
5.1.2
Setting the capacity (open vented heating
systems)
In open systems, the hydrometer needle must lie within
the red field.
z
Set the green needle on the hydrometer to the required
capacity.
z
Top up the heating water or drain via the boiler fill and
drain valve until the required capacity has been
reached.
Fig 59 Hydrometer for open systems
1
Hydrometer needle
2
Green needle
3
Red field
5.2
Start up the control panel
Please see the accompanying technical documentation
for the 4000 series control panel for information about on
how to start it up.
5.3
Commission the burner
z
When commissioning the burner, follow the
instructions in the technical documentation enclosed
with the burner.
z
Fill out the burner commissioning report.
6304 4901-04.0K
Содержание Logano GE615
Страница 57: ...8 Faults Logano GE615 We reserve the right to make any changes due to technical modifications 57 ...
Страница 58: ...8 Faults Logano GE615 We reserve the right to make any changes due to technical modifications 58 ...
Страница 59: ...8 Faults Logano GE615 We reserve the right to make any changes due to technical modifications 59 ...
Страница 60: ......