2. Inducer Housing Drain Tube
a. Remove and discard LOWER (molded) inducer housing
drain tube which was previously connected to conden-
sate trap.
b. Use inducer housing drain extension tube (violet label
and factory-supplied in loose parts bag) to connect
LOWER inducer housing drain connection to the con-
densate trap.
c. Determine appropriate length, cut, and connect tube.
d. Clamp tube to prevent any condensate leakage.
3. Relief Port Tube
a. Extend collector box tube (green label) which was
previously connected to the condensate trap by splicing
to small diameter tube (factory-supplied in loose parts
bag).
b. Route extended collector box pressure tube to relief port
connection on the condensate trap.
c. Determine appropriate length, cut, and connect tube.
d. Clamp tube to prevent any condensate leakage.
C.
Condensate Trap Field Drain Attachments
Refer to Condensate Drain section for recommendations and
procedures.
D.
Pressure Switch Tubing
The LOWER collector box pressure tube (pink label) is factory
connected to the High Pressure Switch for use when furnace is
installed in UPFLOW applications. This tube MUST be discon-
nected, extended, rerouted, and then reconnected to the pressure
switch in HORIZONTAL LEFT applications for 060 and 080
heating input furnaces.
NOTE:
See Fig. 10 or tube routing label on main furnace door to
check for proper connections.
Modify tube as described below:
1. Disconnect collector box pressure tube (pink label) attached
to High Pressure Switch.
2. Use smaller diameter tube (factory-supplied in loose parts
bag) to extend tube disconnected in item 1.
3. Route extended tube:
a. Behind inducer housing.
b. Between blower shelf and inducer housing.
4. Determine appropriate length, cut, and reconnect tube to
High Pressure Switch connection labeled COLLECTOR
BOX.
E.
Condensate Trap Freeze Protection
Refer to Condensate Drain Protection section for recommenda-
tions and procedures.
F.
Construct a Working Platform
Construct working platform where all required furnace clearances
are met. (See Fig. 3 and 11.)
CAUTION:
UNIT MAY NOT OPERATE
Failure to follow this caution may result in intermittent
unit operation.
The condensate trap MUST be installed below furnace.
See Fig. 5 for dimensions. The drain connection to
condensate trap must also be properly sloped to an open
drain.
NOTE:
Combustion-air and vent pipes are restricted to a mini-
mum length of 5 ft. (See Table 7.)
NOTE:
A 12-in. minimum offset pipe section is recommended
with short (5 to 8 ft) vent systems. This recommendation is to
reduce excessive condensate droplets from exiting the vent pipe.
(See Fig. 11 or 35.)
Fig. 11—Attic Location and Working Platform
A93031
COMBUSTION – AIR
INTAKE
VENT
MANUAL
SHUTOFF
GAS VALVE
SEDIMENT
TRAP
CONDENSATE
TRAP
DRAIN
ACCESS OPENING
FOR TRAP
30
″
MIN
WORK AREA
A 12-IN. MIN HORIZONTAL PIPE
SECTION IS RECOMMENDED WITH
SHORT (5 TO 8 FT) VENT SYSTEMS
TO REDUCE EXCESSIVE
CONDENSATE DROPLETS FROM
EXITING THE VENT PIPE.
5
3
⁄
4
″
NOTE: LOCAL CODES MAY REQUIRE A DRAIN PAN UNDER THE
FURNACE AND CONDENSATE TRAP WHEN A CONDENSING
FURNACE IS INSTALLED ABOVE FINISHED CEILINGS.