Plexus 9000 Planning and Engineering Guide
Planning for Installation
Section 130-200-000
Issue 5, January 24, 2003
Telica, Inc.
6-29
√
Task
Details, see …
_
Plan for at least two trained installation engineers who are
familiar with lifting techniques for heavy objects to be available
to lift and move the chassis and its components to the installation
site from the receiving (unpacking) area.
To reduce the risk, contact your customer service representative
or your trained service personnel for hardware installation and
maintenance.
_
Check that the installation engineers have access to all the tools
required for the installation, including a heavy cart to move the
chassis and its components.
Paragraph
_
Plan the hardware configuration. Make the assignment of system
and I/O modules to slots and provide a configuration map for
installation engineers.
Paragraph
_
Plan the software configuration and system provisioning. Create
a list of parameters that must be provisioned for the Plexus 9000.
6.1.12 Plexus 9000 Configuration
describes what is included when a Plexus 9000 base system
has been ordered. The modules necessary are dependent upon the
application and system requirements.
part numbers, the number required and a column to fill in for the number
required for application.
list spares other than modules that
may be required and
list cables that may be required.