Firstly, close the complete zip fastening of the cladding insulation at each buffer vessel.
►
Position the cover insulation on each SE940 buffer vessel.
►
Route the end of the respective sensor cable harness at each buffer vessel to the back above the cover insulation
and out of the cladding insulation.
►
Position the cover on top of the cover insulation or around the cladding insulation at each buffer vessel.
Note:
For hydraulic (heating water side) connection of the CHP, some pre-assemblies are required.
Take the separately packed components for the respective connection out of the accessory/installation set of
the Dachs Pro 20 ST and have them ready for assembly.
i
Assemble the provided frequency converter according to the manufacturer instructions on a wall near the Dachs Pro 20 ST
overall system.
6.2.5 Frequency converter control box assembly
Reference:
For frequency converter connection, please observe the
instructions in the iav documentation of VW on EcoBlue 2.0
(Generation 1.2) -
Frequency converter connection at Dachs Pro
20 ST
, art. no. 4798.536.xxx.
Attention:
Observe that the provided cable set has a length
of
10 m
and
must not/cannot
be extended.
!
Fig. 43: Frequency converter assembly
- 400 mm -
Gas connection
set
Dachs outlet
connection set
Dachs inlet
connection set
- 500 mm -
- 210 mm -
6.3 Preparations
Содержание Senertec Dachs Pro 20 ST
Страница 115: ...14 4798 495 002 Spare parts 115 Dachs Pro 20 ST Notes ...
Страница 116: ...14 4798 495 002 116 Spare parts Dachs Pro 20 ST Notes ...
Страница 117: ...14 4798 495 002 Spare parts 117 Dachs Pro 20 ST Notes ...
Страница 118: ...Dachs Pro 20 ST Baxi Commercial Wood Lane Erdington Birmingham B24 9QP ...