PN 9000-280-VE, Rev B
Notes About Ducting
Ducting Between Pressurized Enclosure and Inlet
The intake ducting to a compressor should not normally pass through a haz-
ardous area. If the compressor intake line passes through a hazardous area,
it should be constructed of non-combustible material and protected against
mechanical damage and corrosion. Adequate precautions should be taken to
ensure that the ducting is free from leaks in case the internal pressure is below
that of the external atmosphere (see Annex C). Additional protective measures,
for example, combustible gas detectors, should be considered to ensure that
the ducting is free of flammable concentrations of gas vapor.
Additional Purge Time to Account for Ducting
The purge duration should be increased by the time necessary to purge the
free volume of those associated ducts which are not part of the equipment
by at least five times their volume at the minimum flow rate specified by the
manufacturer.
Power for Protective Gas Supply
The electrical power for the protective gas supply (blower, compressor, etc.)
should be either taken from a separate power source or taken from the supply
side of the electrical isolator for the pressurized enclosure.
Enclosure Maximum Overpressure
The user should limit the pressure as specified by the manufacturer.
2-26 | Thermox
®
WDG-V UOP ATEX-IECEx Analyzer
Содержание WDG-V UOP
Страница 1: ...WDG V UOP Combustion Analyzer ATEX IECEx USER MANUAL PN 9000 280 VE_Rev C...
Страница 40: ...PN 9000 280 VE Rev B Figure 2 7 Conduit Entries 2 18 Thermox WDG V UOP ATEX IECEx Analyzer...
Страница 96: ...PN 9000 280 VE Rev B WDG V UOP Series Analyzer Rating Labels 4 6 Thermox WDG V UOP ATEX IECEx Analyzer...