![ABB ACS580MV Скачать руководство пользователя страница 108](http://html1.mh-extra.com/html/abb/acs580mv/acs580mv_hardware-manual_3348342108.webp)
108 Maintenance
Procedure:
1. Open the INU door.
2. Connect the voltage divider probe to the volt-/multimeter and select the appropriate
metering range (see the instruction manuals of the devices).
3. Connect the grounding clip of the voltage divider probe to the cabinet (PE busbar, see
the instruction manual of the probe).
4. Touch the power terminals in front of each power module with the contact electrode of
the probe and check that the voltage is below 50 V.
5. Touch again the power terminals of each power module with the contact tip of the
grounding hook to fully discharge the circuit.
6. Hang the grounding hook to the terminal of the power module to be serviced and leave
it there until work on the module is finished.
7. Make sure again that all power module terminal voltages are below 50 V. Use a
multimeter and measure the voltage between the grounded power terminal and all
other power module terminals before working on the power module.
Starting the drive after maintenance
See Chapter
Operation, Energizing and starting the drive
for instructions on energizing the
drive using the local operator panel of the drive. If the drive is remotely-controlled, follow
the established start-up procedures.
Emergency release of the door safety switch
The door of the INU compartment is secured by a safety switch (item 1 in figure below).
DANGER
Hazardous voltages!
Touching energized components can be fatal.
Before you unlock the safety switch, verify that the drive is de-energized.
Do not unlock the safety switch permanently.
Содержание ACS580MV
Страница 1: ...ABB industrial drives Hardware manual ACS580MV drives 200 kW to 6300 kW 6 kV to 11 kV...
Страница 4: ......
Страница 10: ...10...
Страница 50: ...50 Control system and interfaces...
Страница 52: ...52 Guidelines for planning the electrical installation...
Страница 77: ...Electrical installation 77 Power cable entry from top 1 screen extensions to ground 1...
Страница 90: ...90 Installation checklist...
Страница 125: ...Maintenance 125 5 Disconnect the fiber optic links from the power module 1 Hoist 2 screw M8X20 1 2...
Страница 127: ...Maintenance 127 stops it again 10 Connect the second lifting belts to the lifting eyes provided on the power module...
Страница 142: ...142 Maintenance...
Страница 144: ......
Страница 146: ...Contact us 2UBB004520 Rev E EN 2019 06 27 www abb com drives www abb com drivespartners...