INITIALLY STARTING, CONFIGURING, AND
CHECKING SYSTEM OPERATION
CAUTION!
Performing various steps in the following procedures may cause a service interruption
and/or result in the extension of alarms. Notify any appropriate personnel before starting these
procedures. Also, notify personnel when these procedures are completed.
Initial Startup Preparation
•
Ensure that all blocks, except the last one, in the “Installation Acceptance Checklist” starting on page 11
have been checked.
•
Ensure that module mounting positions are filled by a rectifier module, converter module, or a blank
cover panel, as required. It is acceptable for positions to be left vacant.
•
Refer to the configuration drawing (C-drawing) supplied with your power system documentation for
factory settings of adjustable parameters.
Initially Starting the System
Procedure
1.
Apply battery power to the system by closing the external battery disconnect(s) or protective device(s)
that supplies battery power to the system, if furnished. Close the system’s internal battery disconnect
circuit breakers, if furnished.
2.
Apply AC or DC input power to the system (depending on configuration ordered) by closing ALL
external AC or DC disconnects or protective devices that supply AC or DC input power to the module
mounting shelves. Rectifiers and/or converters automatically start.
3.
Open the distribution cabinet’s front door by turning the latch in the counterclockwise position.
4.
Place each distribution circuit breaker (if furnished) to the ON position.
ACU+ Controller Procedure
Refer to this section if your system is furnished with an ACU+ Controller.
ACU+ Controller Initialization
Refer to the ACU+ Instructions (UM1M820BNA) for detailed instructions.
for locations of the ACU+ local indicators and navigation keys.