Vertiv
|
NetSure 710 Series Installation Manual (IM581127000)
|
Rev. U
12
NOTE!
The system is not powered up until the end of this checklist.
NOTE!
Some of these procedures may have been performed at the factory for you.
Installing the System
Relay Rack Secured to Floor
System Components Mounted in Relay Rack (if required)
Optional Lug Adapter Busbar Kits Installed
Circuit Breakers Installed
Fuses Installed
Setting Jumper and Switch Options
Jumpers on System Interface Circuit Card Set
Factory Switch Setting on IB2 Interface Board Verified
Factory Switch Setting on Optional EIB Interface Board Verified
Factory Switch Setting on Optional SM-DU+ Verified
Making Electrical Connections
Relay Rack Grounding Connection (Frame Ground) Made
Central Office Ground Connection Made
AC Input and AC Input Equipment Grounding Connections Made
External Alarm, Reference, Monitoring, and Control Connections Made
Ethernet Connection Made (if required)
Load Connections Made
Battery Connections Made
a)
Batteries Installed and Connected in an optional Battery Tray (if furnished)
b)
Optional Battery Tray Front Battery Covers Installed (if furnished)
c)
Optional Battery Tray Circuit Breaker Guards Installed (if furnished)
Installing the Modules and Initially Starting the System
Rectifier and Converter Modules Installed
System Started, Configured, and Checked