GEORGIAN INSTALLATION
Carefully point the corners on each side of
the capping where the gaskets abut each
other
50
Seal around the top of each glazing bar top
capping where it meets the rain baffle. Next,
run a bead of sealant along the edge where
the glazing meets the rain baffle.
51
Seal around each glazing bar top capping
where it meets the inner wall of the ‘soft
touch’ moulded weathering shield.
Also apply a bead of sealant to the top
edge of the weathering shield so that the
ridge capping will seal against it when fitted.
52
Run a bead of sealant in the position shown
where the ‘soft touch’ moulded weathering
tray meets the ridge body.
53
Now for the ridge top cap - Cut back the
cresting channel on the top and the T
bolt slot on the underside of the ridge top
capping by 40mm.
54
Now down on the ground take the ridge top
cap assembly and screw the finial into the
radius end capping.
55
Slide the cresting into the ridge channel.
The last section of cresting (by the house
wall) may require cutting to length. Some
cresting options clip over the ridge body.
56
Cut back the underside of the last section
of cresting by 40mm.
57
Apply a bead of sealant into the channel
of the ridge flashing trim before fitting and
then slide into position.
58
40mm
SECTION 4
Summary of Contents for Classic roof